2010-2013 TIP Amendments
June 3, 2010 | March 31, 2010 | January 12, 2010 | December 22, 2009 | September 24, 2009 | August 27, 2009
The following amendments to the 2010-2013 Transportation Improvement Program were made following a meeting of the WWW Board on June 3, 2010.
West Virginia New TIP Projects (Amendments) |
|
|
|
|
U354-14-8.69
STP-0014(136)D
|
WV14-Mineral Wells/Pettyville-Construct 4 lanes from 0.10 miles north of CR 21/34 to 0.04 miles north of CR 21/15. Environmental Assessment.
|
|
FY 2010 |
West Virginia TIP Project Revisions |
Project # |
Project Description |
Revision |
U354-14-7.47
STP-0014(126)D
|
WV14-Mineral Wells-4 lane upgrade from north ramp of I-77 interchange to 0.3 miles east of CR 14/1.
|
Project being changed from an Economic Recovery funded project to a Surface Transportation Program funded project. FY 2011 |
U354-14-18.33
CMAQ-0014(132)D
|
Murdoch Ave. -Intersection improvement at 31 st and 33 rd Streets. Project includes signal installation and improvements and geometric modifications.
|
Cost decreased from $377,000 to $225,000.
FY 2010 |
The following amendments to the 2010-2013 Transportation Improvement Program were made following a meeting of the WWW Board on March 31, 2010.
West Virginia New TIP Projects (Amendments) |
|
|
|
|
S354-68-17.10
ARRA-0068(142)D
|
Juliana Street Bridge-north and south ramps A and B, concrete sealer/latex modified concrete overlay.
|
$2,700,000
(ARRA 2) |
|
S354-2/22-0.02
ARRA-0222 (025)D
|
Bridge replacement on CR 2/22 (Hogland Br.) 0.04 miles south of CR 2/22 and CR2.
|
$450,000
(ARRA 2) |
FY 2010 |
S354-25/13-0.19
ARRA-2513(002)D
|
Bridge replacement project on CR 25/13 (Road Fork Br.) 0.05 miles north of Jackson CR 2/1-0.13 miles north of Jackson CR 2/1. |
$450,000
(ARRA 2) |
FY 2010 |
Unassigned |
WV 14 – Mineral Wells - 4 lane upgrade from north ramp of I-77 interchange to 0.3 miles east of CR 14/1.
|
|
FY 2010 |
T699-STA/UN-2.00
SB-WVSB(905)D
|
Scenic Byway-Staunton Parkersburg Turnpike: Develop branding and marking campaign. Includes Gilmer, Ritchie, Wirt and Wood Counties. |
$70,800 |
FY 2011 |
The following amendments to the 2010-2013 Transportation Improvement Program were made following a phone poll of the WWW Board on January 12, 2010.
West Virginia New TIP Projects (Amendments) |
|
|
|
|
U354-14-16.86
CMAQ-0014(130)D
CMAQ-0014(131)D
|
Vienna-Walmart right turn lane. Construct new right turn lane leading southbound on WV14.
|
$190,000 |
Right-of-Way - FY 2010
Construction - FY 2011
|
S354-95-3.40
STP-0095(069)D
|
WV95-Camden Avenue. Begins at the junction of WV14 and ends at the junction with Cr 21/18. Joint repair, mill existing roadway, resurface with 1.5” slid resistant pavement. Adjust manholes and inlets, temporary and permanent striping.
|
$2,180,000 |
FY 2010 |
U354-14-18.33
CMAQ-0014(132)
|
WV 14: Murdoch Avenue – Intersection improvement at 31 st and 33 rd Streets. Project includes signal installation and improvements, and geometric modifications. |
$376,975 |
FY 2010 |
MOVTA
CMAQ Funds
|
Operational improvement for the Broad Street, Emerson Avenue, and Rayon Drive bus routes. Change headways from one hour to thirty minutes. |
$100,000
(100% federal) |
FY 2010 |
The following amendments to the 2010-2013 Transportation Improvement Program were made following a meeting of the WWW Board on December 22, 2009.
West Virginia New TIP Projects (Amendments) |
|
|
|
|
S354-21/1-0.00
HSIP-0211(001)D
|
Dry Run Road-from the junction of CR 21/1 and CR 4/5. Install guardrails and signs.
|
$18,000 |
FY 2010 |
S354-24-0.00
HSIP-0024(032)D
|
Stillwell Road-Install guardrails and delineation devices.
|
$20,000 |
FY 2010 |
S354-47/21-0.00
HSIP-4721(001)D
|
Cedar Grove Road – East of the junction with WV 47 to west of the junction with WV47. Install rumble strips, pavement markings, and replace signage.
|
$23,000 |
FY 2010 |
U354-LIT/KA-1.00
U354-PAR/K-12
ERP-2009(173)D
CMAQ-2009(214)D
|
Little Kanawha Connector Trail-Expansion of existing bicycle-pedestrian trail in downtown Parkersburg. Project includes combined stimulus (ERP) and Congestion Mitigation Air quality funds (CMAQ). |
$475,000 |
FY 2010 |
The following amendments to the 2010-2013 Transportation Improvement Program were made following a phone poll of the WWW Board on September 24, 2009.
West Virginia New TIP Projects (Amendments) |
|
|
|
|
U354-MOU/NT-1
NRT-2009(159)D
|
Mountwood Park Equestrian Connector Trail-Construct trail between Mountwood Park and North Bend Rail Trail.
|
$41,000 |
FY 2010 |
U354-PAR/KE-11.00
TEA-OH22(001)D
|
Parkersburg 5th Street Streetscape-Construction of sidewalks and ADA compliant curb cuts, installation of period lighting, pedestrian amenites, and landscaping from Juliana Street to the Belpre Bridge. |
$250,000 |
FY 2010 |
U354-JEF/FE-1
SRTS-2009(148)D
|
Jefferson Elementary Center-Construction and improvement of sidewalk on school property and City of Parkersburg Streets. Education, encouragement and evaluation components. |
$110,000 |
FY 2010 |
The following amendments to the 2010-2013 Transportation Improvement Program were made following a phone poll of the WWW Board on August 27, 2009.
West Virginia New TIP Projects (Amendments) |
|
|
|
|
X354-50-7.00 12
APD-0282(145) D |
US 50: WV 47 interchange – Blennerhassett Bridge. Seeding, mulching, and bank stabilization.
|
$400,000 |
FY 2010 |
West Virginia TIP Project Revisions |
Project # |
Project Description |
Revision |
U354-2-23.11 02
EB-0002(438) D |
WV2: Bridge over I-77 0.16 miles north of CR 4/6. Replace/widen bridge and approach. |
Total project cost increase from $9,200,000 to $13,410,000. Project being moved from FY 09 to FY 12 with advanced construction and payback of advanced construction in FY 13. Federal funding changed from stimulus funds to Equity Bonus. |
S354-77-173.72
IM-0773(257)
NH-0773(257) |
I-77 – widen to 6 lanes from north Camden Avenue interchange to Staunton Avenue interchange. Includes two bridges. |
Total project cost increase from $19,559,000 to $32,340,000. Includes both Interstate Maintenance (IM) and National Highway System (NH) funds. |
|