West Virginia New TIP Projects (Amendments) |
|
|
|
|
U354-14-13.57
CMAQ-0014(105)E
|
WV 14 and Green Street – Construct dual right turn lanes. |
Increased from $655,000 to $800,000
|
Include right-of-way phase to existing project in FY 2008.
|
S354-WET/LA-1
STP-0002(453)D
|
Wetland Acquisition (McPherson Property) |
$125,000 |
FY 2008 |
U354-WIL/LI-2
NRT-2007(116)D
|
Williamstown-wetland walking trail. |
$50,000 |
FY 2008 |
U354-2-23.11 03
NH-0002(384)D
|
WV 2 – Reconstruct to 5 lanes from CR 16/3 to CR 3/8. |
Increase from $8,456,000 to $9,132,000 |
Construction moved from FY 2009 to FY 2011. |
U354-14-7.47
STP-0014 (090)D
STP-0014 (067)D
|
WV 14 – Upgrade to 4 lanes from north ramp of I-77 interchange to 0.3 miles east of CR 14/1. |
Increase from $9,190,000 to $9,830,000 |
Right-of-Way moved from FY 2008 to FY 2009 Construction moved from FY 2009 to FY 2011
|
U354-14-8.69
STP-0014 (113)D
|
WV14 – Pettyville – 4 lane upgrade |
Decreased from $8,950,000 to $8,635,000 |
Right-of-Way moved from FY 2008 to FY 2010 Construction moved from FY 2009 to FY 2011
|
S354-77-173.22
IM-0773 (273)D
|
Replace deck and widen to 6 lanes on I-77 interchange bridge over WV 95/ Camden Avenue. |
Increase from $2,876,000 to $3,199,000 |
Construction moved from FY 2009 to FY 2010 |
West Virginia TIP Project Revisions |
Project # |
Project Description |
Revision |
U354-95-4.84
NHG-0095(068)D
|
Signal Renovation at intersection of Camden Ave. and Broadway Ave.
|
Cost increase from $385,632 to $422,168. |
S354-50-13.50 00
NH-0050(260)D
|
US50 – Resurfacing from 0.22 miles west of CR 50/35 to 2.10 miles east of CR5.
|
Cost increase from $1,488,240 to $2,800,000.
|
S354-77-173.72
IM-0773 (257)
NH-0773 (361)
|
I-77 – Safety upgrade and widening from .7 miles south of WV 47 to the north end of WV 47 bridge.
|
Cost increase from $19,509,000 to $19,559,000. Project being moved from FY 2009 to FY 2010.
|
Ohio New TIP Projects (Amendments) |
|
|
|
|
PID 83919
WAS-Marietta River Trail (Phase 3)
|
Extension of Marietta River Trail Bike/Pedestrian path, approximately 1.3 miles and includes construction of Bridge over Duck Creek. Begins at 4 th Street near Ohio River and ending on north side of Duck Creek.
|
$1,190,500 |
FY 2010 |
PID 83805
WAS-SR7-39.33
|
Landslide repair. Beginning at 0.34 miles south of CR 244.
|
$699,050 |
FY 2011 |
| Ohio TIP Project Added For Informational Purposes Only |
Project # |
Project Description |
Total Project Cost |
Schedule |
PID 83787
PID Pavement Marking |
Pavement marking project. |
$1,843,000 |
FY 2013 |
PID 83788
D 10 - HS
|
Herbicidal spraying on various routes and sections in District 10. |
$100,000 |
FY 2013 |
West Virginia New TIP Projects (Amendments) |
|
|
|
|
U354-2-23.11 02
EB-002(438) |
WV2-Bridge over I-77 0.16 miles north of CR 4/6. Replace and widen bridge and approach. |
Changed from $8,213,000 to $9,199,000. Federal share of construction phase changed from $6,670,000 to $7,358,000. |
Project remains in FY 2010 |
U354-14-11.08 00
CMAQ-0014 (108) E
CMAQ-0014 (109) E
CMAQ-0014 (110) E |
WV14/Gihon Rd. - Intersection improvements including the construction of a right turn lane from 500’ south of Gihon Rd. to 500’ north Gihon Rd. |
Changed from $900,000 to $951,000. Federal share of construction phase changed from $300,000 to $400,000. |
Engineering phase moved from FY 2009 to FY 2008
Construction phase moved from FY2010 to FY 2009 |
U354-14-13.57
CMAQ-0014 (105) E |
WV14 and Green Street – 400’ west of 5 th St. to 400’ south of Green Street – Dual right turn lanes. |
Changed from $595,000 to $655,000. Federal share of construction phase changed from $468,000 to $516,000. |
Project remains in FY 2008 |
U354-14-15.19 00
NHG-0014 (107) E |
Sign renovation project from the intersection of WV14 and WV68 to the intersection of WV14 and CR 21/39 in Vienna. |
Changed from $400,000 to $428,000. Federal share of construction phase changed from $400,000 to $428,000. |
Project remains in FY 2008 |
S354-32-0.40
BR-0032 (024) E |
Wood CR 32 – Replace Sundowner Bridge over Neal Run, 0.05 miles west of CR 32/3. |
Changed from $1,318,000 to $1,404,000. Federal share of construction phase changed from $1,040,000 to $1,123,000. |
Right-of-way phase deleted
Construction phase remains in FY 2009 |
X354-D-0.63 06
APD-0282 (143) E |
River Hill Road Bridge – Construct bridge from 0.13 miles north of Corridor D to 0.15 miles north of Corridor D. |
Changed from $5,196,000 to $5,533,000. Federal share of construction phase changed from $4,252,000 to $4,266,000. |
Project remains in Fiscal Year 2008 |
U354-47-2.75 00
STPG-0047 (045) E |
New signal at the WV 47/I-77 SB exit/entrance ramp. Modification of the WB exit/entrance ramp. |
Changed from $280,000 to $300,000. Federal share of construction phase changed from $280,000 to $300,000. |
Project remains in FY 2008 |
S354-50-3.43
BR-0050 (147) E |
Renovate Winans Arch culverts at Worthington Cr. 0.3 miles east of CR 50/44. |
Changed from $385,000 to $464,000. Federal share of construction phase changed from $280,000 to $351,000. |
Contract plans remain in Fiscal Year 2008
Construction remains in Fiscal Year 2011 |
U354-50 - 4.83 00
NHG – 0050 (271) E
NHG – 0050 (272) E |
US 50 – Sign renovation, various locations. |
Changed from $1,250,000 to $1,071,000. Federal share of construction phase changed from $1,000,000 to $1,071,000. |
Construction phase moved from Fiscal Year 2008 to Fiscal Year 2010 |
S354-50-9.44 00
NH-0050 (259) E |
US 50 – Resurface (1.5”) from CR 50/37 to 0.22 miles west to CR 50/35. Includes guardrails. |
Changed from $1,275,000 to $1,568,000. Federal share of construction phase changed from $1,020,000 to $1,254,000. |
Construction phase remains in Fiscal Year 2011 |
S354-50-13.50 00
NH-0050 (260) E |
US 50 – Resurface (1.5”) from 0.22 miles west of CR 50/35 to 2.10 miles east of CR 5. |
Changed from $1,350,000 to $1,488,000. Federal share of construction phase changed from $1,080,000 to $1,191,000. |
Construction phase remains in Fiscal Year 2008 |
U354-68-1.66
CMAQ-0068 (127) E |
WV 68 and Ann Street – Addition of right turn lane. |
Changed from $225,000 to $247,000. Federal share of construction phase changed from $174,000 to $191,000. |
Engineering and construction phase remain in Fiscal Year 2008 |
U354 – 68 – 19.96
CMAQ – 0068 – (129) E
CMAQ – 0068 – (130) E
CMAQ – 0068 – (131) E |
WV 68 – Emerson Ave./36 th Street intersection realignment. Includes signal renovation and construction of turn lane on 36 th St.. |
Changed from $650,000 to $691,000. Federal share of construction phase changed from $228,000 to $261,000. |
Engineering phase moved from Fiscal Year 2009 to Fiscal Year 2008. Right-of-way phase remains in Fiscal Year 2009. Construction phase moved from Fiscal Year 2010 to Fiscal Year 2009. |
S318 - 0 77 – 144.00
IMG – 0773 (378) E |
I-77 sign renovation project from Ravenswood interchange to Ohio State line. |
$1,000,000 |
Construction phase moved from Fiscal Year 2008 to Fiscal Year 2010 |
S354-77-157.00 00
IM-0773 (392) E |
I-77 – Resurface (1.5”) from Jackson Co. line to CR 21/31 overpass. Includes removing overlay, paving shoulders, and guardrails. |
Changed from $1,150,000 to $1,365,000. Federal share of construction cost changed from $1,035,000 to $1,229,000. |
Construction phase moved from Fiscal Year 2010 to Fiscal Year 2011 |
S354-77-160.34
IM-0773 (389) E |
I-77 – Resurface (1.5”) remove overlay, pave shoulders, guardrails from CR 21/31 overpass to CR 21/24 overpass. |
Changed from $1,700,000 to $2,090,000. Federal share of construction phase changed from $1,530,000 to $1,881,000. |
Construction phase moved from Fiscal Year 2011 to Fiscal Year 2012 |
S354-77-181.93 00
IM-0773 (390) E |
I-77 NB – Resurface (1.5”) from 1.87 miles north of WV2 interchange to the Ohio River Bridge. Includes removing overlay, paving shoulders and guardrails. |
Changed from $1,350,000 to $1,603,000. Federal share of construction phase changed from $1,215,000 to $1,442,000. |
Construction phase moved from Fiscal Year 2010 to Fiscal Year 2011 |
S354-77-173.72
IM-0773 (257)
NH – 0073 (361) |
Widen I-77 to 6 lanes including two bridges from .7 miles south of WV 47 to the north end of WV 47 bridge ( Staunton Avenue interchange – safety upgrade). |
Changed from $17,588,000 to $19,509,000. Federal share of construction phase changed from $15,196,000 to $16,904,000. |
Right-of-way remains in Fiscal Year 2008.
onstruction remains in Fiscal Year 2009.
|
T654-77-186.79 00
BR-NBIS (356) E |
Williamstown/Marietta Br. Over Ohio River. 6 year inspection. |
$480,000 |
Project moved from Fiscal Year 2009 to 2008 |
U354-95-4.84
NHG-0095 (068) E |
Intersection of Camden Avenue and Broadway Avenue – Signal renovation project. |
Changed from $360,000 to $386,000. Federal share of construction phase changed from $360,000 to $386,000. |
Construction phase remains in Fiscal Year 2008 |
West Virginia TIP Project Revisions |
Project # |
Project Description |
Revision |
S354-14-18.34 00
NH-0014 (101) E |
WV 14 – Grand Central Avenue – Resurface (1”) from 0.74 miles south of CR 12 to 0.18 miles south of CR 21/4. |
Deleted |
S354-47-8.22 00
STP-0047 (041) E |
WV 47 – Resurface (1”) from 1.19 miles east of CR 47/17 to CR 47/10. |
Deleted |
S354-50-5.67 00
NH – 0050 (249) E |
US 50 – Resurface (1.5”) beginning milepost 5.67 to 0.9 miles west of CR 50/4. Project includes guardrails. |
Deleted |
S354-68-0.00 00
STP-0068 (124) E |
WV 68 – Resurface (1”) from Jackson Co. line to CR 2/2. |
Deleted |
354-68-19.06 00
NH-0068 (122) E |
WV 68/ - Emerson Avenue – Resurface (1”) rotomill from WV 14 to 0.03 miles south of CR 2/7. |
Deleted |
S354-95-3.40 00
NH – 0095 (067) E |
WV 95 – Camden Avenue – Resurface (1”) from WV 14 to CR 21/16. |
Deleted |
Ohio New TIP Projects (Amendments) |
|
|
|
|
PID 82958
WAS-Marietta Detour Study |
Marietta : Traffic operations study in preparation for Washington Street Bridge closure. |
$37,300 |
FY 2008 |
PID 82996
WAS-50-01.97 LT |
Belpre Township : Concrete deck overlay. |
$355,900 |
FY 2011 |
PID 83259
WAS-CR9-4.91 |
Newport and Lawrence Townships: Full depth resurfacing, plus guardrail and pavement marking. |
$601,400 |
FY 2009 |
PID 83255
WAS-CR10-00.00 |
Constitution, Warren Township: Repair joints and base concrete, resurfacing with asphalt, apply pavement markings. |
$287,875 |
FY 2011 |
PID 83253
WAS-CR51-00.00 |
Belpre and Dunham Townships: Repair joints and base concrete, resurface with asphalt, apply pavement markings. |
$138,010 |
FY 2011 |
PID 82799
WAS-US50-8.61 |
Construct two left turn lanes at the intersection of WAS SR7 and Braun Rd., add two left turn signal heads. Revise project to include the same improvement at the intersection of SR 7 and Farson St. |
Revised from $359,817 to $719,634. MPO funding to be capped at $575,707. |
FY 2010 |
Ohio TIP Project Revisions |
|
|
|
PID 79105
WAS-SR618-3.80 |
Belpre: Intersection improvement at Farson Street and SR618. Work includes construction of a through lane and possible signal pole relocation. |
Increase MPO funding from $244,000 to $259,659.92. |